Development Works in the 13th ward as on 20.08.2018

Type of
Grant

Name of the work

Estimated Amount

Stage of work

SFC

Providing WBM Road from Vadranam Raja Rao House to Karra Johnpaul House at 13th ward Mondi Kalavakatta.

3.38

Completed

SFC

Construction of CC Drains from Chebrolu Giri House to Mande Devadasu House at 13th ward

3.02

Completed

GF

Providing C.c Road from Vadranam Sudhakar House to Mandru Yacob House at 13th ward

2.28

Completed

GF

Providing Retaining wall at  Vadimukalla Culvert

1.00

Completed

GF

Construction of CC Drains from Chebrolu Giri House to Mande Devadasu House at 13th ward

2.92

Completed

GF

Repairs School Building at Special Municipal Elementary School Vaddimukkala Road 13th ward

0.43

Completed

SDF

Providing C.C.Drain at 13th ward ward in Ponnur Municipality

1.50

Work to be Started

SCSP

Construction of CC Drains from Katti Srinivasa Rao House Gugilam Seshaya House at Ambedkar Nagar 13th ward

6.00

Completed

SCSP

Construction of CC Drains fromEdu Somaiah House to Rati krind Koteswara Raoat Ambedkar Nagar 13th ward

2.87

Completed

SCSP

Construction of CC Drains from Boleddu Rataiah House to Katti Srinivasa Rao House at Ambedkar Nagar 13th ward

4.30

Completed

SCSP

Construction of CC Drains from Yatati Bhavanarayana House Mandru Adam at Ambedkar Nagar 13th ward

5.85

Completed

SCSP

Construction of CC Drains from Mandru Ankinidu House Rati Krinda Koteswara Rao at Ambedkar Nagar 13th ward

4.20

Completed

SCSP

Construction of CC Drains from  Farre Sanjeva Rao House to Valaparla Adam at Ambedkar Nagar 13th ward

2.20

Completed

SCSP

Construction of CC Drains from Yattati Ravi House to Yattati Kiran House at Ambedkar Nagar 13th ward

2.88

Completed

SCSP

Construction of CC Drains from Gajulaparthi Prasad House to Pondugula Suresh House at Ambedkar Nagar 13th ward

3.20

Completed

SCSP

Providing Drain from Adam House to Alladi Devid House at 13th ward  in  Ponnur Municipality

3.80

Completed

SCSP

Leveling the  Community site at vaddimukkala road at 13th ward

4.80

Completed

SCSP

Leveling of 12th & 13th wards burial grounds

3.20

Completed

SCSP

Protection of Mondi Kaluva from Repalle Road to Vaddimukkala Road in Ponnur Municipality - Package-I

49.99

Completed

SCSP

Protection of Mondi Kaluva from Repalle Road to Vaddimukkala Road in Ponnur Municipality - Package-II

49.98

Completed

SCSP

Construction of C.C Road from Kanneganti Arjuna Rao House to Yathati Seshaiah House at 13th & 14th Ward in Ponnur Municipality.

32.61

Completed

SCSP

Providing CC road from John Paul house to V Rajendra Prasad House 13th ward

7.86

Work order issued, Agreement to be concluded

SCSP

Providing CC Slab Culvert crossing between V. Raju road to Ch. Mariammah road 13th ward

2.22

Work order issued, Agreement to be concluded

SCSP

Construction of C.C.Road and Drain from D Naga Raju House to K Pitchaiah House at 13th ward

3.99

Work order issued, Agreement to be concluded

SCSP

Providing CC road from Ch Mariyamma House to K Arjun House 13th ward

8.10

Work order issued, Agreement to be concluded

SCSP

Widening of CC road from Chrch at  Repalle road to Vattimukkala road 13th ward in  Ponnur Municipality

21.47

Work order issued, Agreement to be concluded

SCSP

Construction of Community Centre at 13th ward Nidubrolu

34.32

Work order issued, Agreement to be concluded

Total Estimation Cost

268.37