Development Works in the 5th ward as on 20.08.2018

Type of
Grant

Name of the work

Estimated Amount

Stage of work

13th finance

Construction of C.C.Drains at Duffpet

27.47

Completed

Non-PG

Ponnur Municipality - Providing C.C.Road from ASM College gate to NMSchool road at 5th ward under  Non plan grant

3.12

Completed

GF

Providing C.C.Road road widening  beside MRO Office at 5th ward

2.90

Completed

GF

Providing C.C.Roads from Baji House to culvert at 1st lane Duffpet - 5th ward

6.50

Completed

GF

Construction of Anna Canteen Compound Wall at 6thWard in Ponnur Municipality

6.00

Work is in Progress

14th finance

Providing C.C.Drain from Shaik Khudus house to Shaik Kasim house in 1st lane Dufpet 5th ward in Ponnur Munucipality

4.25

Completed

14th finance

Providing C.C. Road from Sk Gouse  (H) to Julfikar Ali Beig 5th  Ward in Ponnur Municipality

8.80

Completed

SDF

Construction of C.C.Road from C.C.Culvert to North side Compound wall at Duffpet in 5th ward

1.65

Completed

SDF

Providing CC raod  from Abdul Shukur House to C.C.Road Last  5th  ward in  Ponnur Municipality

1.50

Work to be Started

SFC

Providing CC road from Sk Asha Bee (H) to Patan Ali Khan at 5th ward

8.15

Work to be started

SFC

Providing CC raod  from Existing culvert to ASM Collecge  at 5th ward in  Ponnur Municipality

4.40

Work order issued, Agreement to be concluded

SFC

Construction of CC Drain from Duff Pet Culvert at 4th lane to South side Culvert at 5th ward  in Ponnur Municipality.

0.98

Work order issued, Agreement to be concluded

SFC

Construction of CC Drain from  Advacate Ajeez House to Sridevi Studio at 5th ward  in Ponnur Municipality.

1.79

Work order issued, Agreement to be concluded

SFC

Construction of CC Drain from  Muneer Tent House to Raja Studio and Culvert at Opp S S Hak Hospital at 5th ward  in Ponnur Municipality.

2.16

Work order issued, Agreement to be concluded

Total Estimation Cost

79.67